Planning and Overseeing Capital Projects in a Condominium Corporation

Why Capital Projects Deserve a Plan Before They Need One
Most condominium corporations will face a major capital project at some point: a building envelope repair, a roof replacement, a parking garage restoration or an elevator modernization. These projects are rarely small, and they rarely arrive at a convenient time. The boards that handle them well are usually the ones that treated the project as a managed process from the first conversation, not as an emergency to be resolved once a failure has already occurred.
This guide outlines how Ontario condominium boards can approach a capital project in a structured way, from defining the scope to closing out deficiencies. It is general information, not legal or engineering advice, and boards should consult their solicitor and engineer on the specifics of their property.
Start With the Scope, Not the Contractor
The most common early mistake is asking contractors what needs to be done. A contractor has a legitimate interest in the work being larger, and without an independent assessment the board has no reliable basis for comparing proposals.
A defined scope typically begins with the evidence already available. A reserve fund study will identify components approaching the end of their expected life and will give a projected cost and timing. Condition assessments, prior repair records and resident complaints, such as recurring leaks, help to confirm where the real problems lie. Together they let the board answer three questions: what needs to be done, why it needs to be done now, and what happens if it is deferred.
If you have not reviewed your most recent study recently, this is the moment to do so. Reserve fund planning and capital planning are the same conversation, and the study is where the board’s funding picture is set out. Under sections 93 and 94 of the Condominium Act, 1998, Ontario corporations are required to conduct reserve fund studies and to maintain a plan for funding future major repairs and replacements.
Engage Independent Engineering Support Early
For anything beyond routine repairs, the board should retain a qualified engineer or consultant who is independent of the contractors who will bid on the work. The consultant’s role is generally to investigate conditions, prepare a specification and drawings, support the tender process and review the work as it proceeds.
The value of that independence is practical. A specification written by someone with no interest in the outcome allows bids to be compared on the same basis, and it gives the board a professional opinion to rely on when making decisions that residents will question. Engineering fees are a real cost, but they are generally modest relative to the cost of a poorly specified project.
Understand What Owner Notice and Approval May Be Required
Not every capital project is treated the same way under the Act. Repairs and replacements of existing common elements are normally part of the corporation’s ordinary responsibilities, while a substantial addition, alteration or improvement to the common elements can trigger notice requirements to owners and, in some cases, an owner vote. Section 97 of the Condominium Act, 1998 deals with this area, and the thresholds and procedures matter. Before a board commits to a project that goes beyond like-for-like replacement, it should confirm with its solicitor whether section 97 applies and what the corporation’s own declaration and by-laws add.
Funding deserves the same early attention. If reserve fund balances will not cover the work, the board will need to decide how to bridge the gap, whether through a special assessment, a loan or phasing the work. Owners respond better to a plan that is explained in advance than to a notice that arrives after the contract is signed.
Run a Disciplined Tender
A well-run tender does not have to be complicated, but it does have to be consistent. Every bidder should receive the same documents and the same deadline, and should have the same opportunity to ask questions, with answers shared with all parties.
When the bids arrive, price is only part of the evaluation. Boards should look at:
The contractor’s experience with comparable work on occupied residential buildings.
References from other condominium corporations, which should actually be called.
Insurance coverage and Workplace Safety and Insurance Board (WSIB) clearance.
The proposed schedule, site supervision and how residents will be kept informed.
Any exclusions or allowances that make a low bid less competitive than it first appears.
The lowest bid is not automatically the best. A price that is significantly below the others deserves a closer look to determine what has been left out.

Oversight Is Where Projects Succeed or Fail
Once construction begins, the board’s attention often shifts to the next agenda item. This is where problems tend to develop. Ongoing oversight should include regular site reviews by the consultant, written reporting to the board, a clear process for change orders and a record of what was approved and why.
Change orders deserve particular care. Some are unavoidable, since hidden conditions are common in older buildings, but each one should be documented, priced and approved before the work proceeds, not reconciled at the end of the project.
Communication with residents is part of the work as well. Noise, access restrictions and scaffolding affect people’s daily lives. Clear notices, a named point of contact and honest timelines reduce complaints considerably, and they keep the board from absorbing frustration that is better answered by good information.
Manage Deficiencies and Close the Project Properly
Substantial completion is not the end of the project. Before final payment, the consultant should prepare a deficiency list, the contractor should correct the items, and the board should confirm that corrections have been made. Holdbacks, warranties and the documentation of as-built conditions should all be reviewed before the file is closed.
Warranty terms are worth recording in a place where future boards will find them. A defect that appears in year two is far easier to resolve when the warranty, the contractor’s contact details and the original specification are on file.
Where Dedicated Project Management Support Adds Value
Boards are made up of volunteers, and a capital project can demand more time than most directors can reasonably give. A capable property manager does not replace the board’s decision-making authority, but carries much of the coordination: gathering records, managing the tender documents, keeping the consultant and contractor on schedule, tracking the budget against the reserve fund and reporting to the board in a form that supports informed decisions.
Capital projects also place demands on a property manager that sit alongside the daily work of running a building. At GIA, we have a dedicated project management team that works with each corporation’s property manager, so a major project receives focused attention and does not compete with day-to-day operations. For the board, that means one coordinated team, with the project’s schedule, budget and reporting managed with the same care as the building itself.
That depth of support is a significant part of what GIA provides to the condominium corporations we manage, alongside the financial administration and governance support described on our services page. If you are comparing management approaches, our list of the property types we serve and our company background offer more detail on how we work.
Request a Proposal
If your board is preparing for a major capital project, or is not confident that your current management company has the capacity to oversee one, we would be glad to discuss how GIA could support your corporation. We provide tailored proposals following an assessment of your property’s size, complexity and needs.